BEE/EESL's energy savings project implementations in the Agriculture sector

Last Modified: Wed Jan 20 2016 22:14:15 GMT+0530 (India Standard Time)
  • 590
    pump sets replaced as part of the Hubli Ag DSM project in Karnataka, at a cost of 2.60 crore resulting in 37% energy savings.
  • 1337
    pump sets replaced as part of the CESC Mysore Ag DSM project in Karnataka, at a cost of 5.03 crore resulting in 37% energy savings.
  • 2496
    pump sets under replacement as part of EPDC Rajanagaram Ag DSM project in Andhra Pradesh, at current investment of 19.66 cr. Estimated 30% energy savings.
  • 50,000 pumps
    will be targeted as part of expansion of the 3 initial pilot projects. These will be executed as part of 7 projects, across the states of Andhra Pradesh, Uttar Pradesh, Rajasthan and Kerala.