Jalyukt Shivar Abhiyan Progress Tracker

Last Modified: Sat Apr 01 2017 09:11:05 GMT+0530 (India Standard Time)
  • 4,557
    out of a total 6,951 works completed in Ahmednagar as on 16-May-16 [65.55%]. 376 works completed since mid May.
  • 824
    out of a total 2,347 works completed in Akola [35.01%] - 24 completed since mid May.
  • 1,084
    out of a total 5,199 works completed in Amravati [20.85%]. Only 17 added since mid-May
  • 1,698
    out of a total 4,362 works completed in Aurangabad [37.86%]. 229 works completed since mid May
  • 248
    out of a total 1,583 works completed in Bandara [15.67%]. Only 42 works completed since mid May.
  • 922
    out of a total 3,551 works completed in Beed [25.96%]. 203 works completed since mid May.
  • 2,493
    out of a total 9,451 works completed in Buldana [26.38%]. 137 works completed since mid May.
  • 5,252
    out of a total 11,290 works completed in Chandrapur [46.52%]. 1,019 works completed since mid May.
  • 1,323
    out of a total 2,396 works completed in Dhule [55.22%]. 162 works completed since mid May.
  • 1,417
    out of a total 3,818 works completed in Gadchiroli [37.11%]. Only 70 works completed since mid May.
  • 422
    out of a total 2,164 works completed in Godiya [19.50%]. Only 73 works completed since mid May.
  • 412
    out of a total 2,284 works completed in Hingoli [18.33%]. Only 4 works completed since mid May.
  • 1,622
    out of a total 5,152 works in Jalgaon [31.48%]. 209 works completed since mid May.
  • 566
    out of a total 4,955 in Jalna [11.42%]. Only 37 works completed since mid May.
  • 413
    out of a total 1,924 in Kolhapur [21.46%]. 27 works completed since mid May.
  • 533
    out of a total 5,533 in Latur [9.99%]. Only 72 works completed since mid May.
  • 2,062
    out of a total 3,846 in Nagpur [53.61%]. Only 98 works completed since mid May.
  • 1,770
    out of a total 4,349 in Nanded [40.70%]. Only 40 works completed since mid May.
  • 1,542
    out of a total 2,815 in Nandurbar [54.78%]. Only 69 works completed since mid May.
  • 2,538
    out of a total 5,703 in Nashik [44.50%]. 479 works completed since mid May.
  • 4,134
    out a total 11,145 in Osmanabad [37.09%]. 1,702 works were completed since mid May.
  • 448
    out of a total 1,808 in Palghar [24.78%]. 361 works completed since mid May.
  • 844
    out of a total 3,728 in Parbhani [22.64%]. Only 31 works completed since mid May.
  • 2,405
    out of a total 5,316 in Pune [45.24%]. 182 works completed since mid May.
  • 446
    out of a total 760 in Raigad [58.68%]. 105 works completed since mid May.
  • 841
    out of a total 1,719 in Ratnagiri [48.92%]. 293 works completed since mid May.
  • 1,391
    out of a total 4.016 in Sangli [34.66%]. 165 works completed since mid May.
  • 2,659
    out of a total 5,768 in Satara [46.10%]. 136 works completed since mid May.
  • 225
    out of a total 556 in Sindhudurg [40.47%]. 15 works completed since mid May.
  • 12,225
    out of a total 23,972 in Solapur [51.00%]. 496 works completed since mid May.
  • 1,406
    out of a total 3,000 in Thane [46.87%]. 589 works completed since mid May.
  • 662
    out of a total 7,695 in Wardha [8.20%]. 32 works completed since mid May.
  • 1,167
    out of a total 2,567 works completed in Washim [45.46%]. 129 works completed since mid May.
  • 782
    out of a total 9,872 works completed in Yavatmal [7.92%]. Only 37 works completed since mid May.