Accelerated Irrigation Benefit Programme,Maharashtra (AIBP) Priority I projects in Maharashtra

Last Modified: Mon Jan 02 2017 23:02:48 GMT+0530 (India Standard Time)
  • 7
    projects have been identified as Priority I and are required to be completed by 2016-17.
  • 15.99 tha
    current irrigation potential of Waghur Irrigation Project (in thousand hectares). 41.45% of target achieved [Target: 38.57 tha].
  • 27.45 tha
    current irrigation potential of Bawanthadi Irrigation Project. 99% of target achieved [Target: 27.71 tha].
  • 29.76 tha
    current irrigation potential of Lower Dudhna Irrigation Project. 66.9% of target achieved. [Target: 44.48 tha].
  • 4.97 tha
    current irrigation potential of Tillari Irrigation Project. 75.64% of target achieved. [Target: 6.57 tha].
  • 18.76 tha
    current irrigation potential of Lower Wardha Irrigation Project. 29.62% of target achieved. [Target: 63.33 tha].
  • 3.57 tha
    current irrigation potential of Lower Panzara Irrigation Project. 47.00% of target achieved. [Target: 7.59 tha].
  • 0 tha
    current irrigation potential of Nandur Madhmeshwar Ohase II Irrigation Project. 00.00% of target achieved. [Target: 11.56 tha].