6 MW
planned generation capacity of solar based installations at the Brisbane airport. The capacity will be built over 6 stages and at 6 sites.
-
9,315 MWh
of electricity that will be generated each year.
-
6%
of the airport's electricity consumption will be met.
-
8,000 tonnes
estimated reduction in carbon emissions each year.
-
6
sites where the solar panels will be installed. 36,000 sq. meters of surface area, more than twice the size of the Melbourne Cricket Ground (MCG), will be used to install the solar panels
-
19,200
solar panels will be used in all.
-
$11 million
estimated project cost. Epho Solar - an Australian commercial solar company - has been awarded the contract to implement the project.
-
40
jobs will be created.
-
$1 million
estimated savings in electricity bills once all the 6 sites are fully operational.
-
Jul 2017
start of construction. Completion of all 6 stages expected by Dec 2018.