Year wise progress of Myanmar's Phase I rural electrification plan

Last Modified: Sun Apr 08 2018 10:47:34 GMT+0530 (India Standard Time)
  • 2016 - 2021
    Period for Phase I. the execution will be carried out by the Department of Rural Development, Ministry of Agriculture, Livestock and Irrigation (MOALI).
  • 8,400
    Number of villages where solar home systems will be installed.
  • 460,000
    households in these villages will be provided with rooftop solar or solar home systems.
  • 350
    Number of villages where mini-grids will be set up.
  • 35,000
    households to be receive power generated from mini-grid systems.
  • 23,000
    Number of new “community” connections for clinics, schools and religious buildings that will be created.
  • 150,000
    public lights that will be put up.
  • 30 MW
    of overall capacity is expected to be generated through the above installations.
  • 2016 - 2017
    First year of the program
  • 2,708
    Number of villages where solar home systems have been installed.
  • 10
    Number of villages powered through mini-grid installations.
  • 140,000
    Number of households electrified.
  • 2017 - 2018
    Year 2 of the program.
  • 1,300
    Number of villages where solar home systems will be taken up for installation.
  • 34
    Number of villages that are planned to be powered through mini-grid installations.
  • 80,000
    Number of households that will be electrified.