  • 80 MLD
    Naini Sewage Treatment Plant within Sewerage District A. Situated on the right bank of river Yamuna. 60 MLD capacity was commissioned in 1998 and an additional 20 MLD commissioned in 2013. STP is based on ASP + Chlorination Technique.
  • 60 MLD
    Rajapur Sewage Treatment Plant within Sewerage District D. Situated on the bank of river Ganga in Mehdauri Kachhar. 30 MLD capacity was commissioned in 2013 and an additional 30 MLD commissioned in Mar 2016. STP is based on UASB + Aerated Lagoon followed by Chlorination technique.
  • 43 MLD
    Salori Sewage Treatment Plant within Sewerage District C. Situated on the right bank of river Ganga. 29 MLD capacity was commissioned in 2007 and an additional 14 MLD commissioned in ?. STP is based on MBBR technique.
  • 25 MLD
    Kodra Sewage Treatment Plant within Sewerage District E. Situated on the right bank of river Ganga. 25 MLD capacity was commissioned in ?. STP is based on high rate bio-filtration + Chlorinaion technique.
  • 10 MLD
    Ponghat Sewage Treatment Plant within Sewerage District E. Situated on the right bank of river Ganga. 15 MLD capacity was commissioned in ?. STP is based on high rate bio-filtration + Chlorinaion technique.
  • 80 MLD
    Numayadahi Sewage Treatment Plant within Sewerage District B. Situated on the left bank of river Yamuna. 50 MLD capacity was commissioned in 2013, additional 30 MLD commissioned in 2018. STP is based on high rate bio-filtration + Chlorination technique.
  • 11.62 MLD
    Allapur Sewage Treatment Plant within Sewerage District C. Situated on the ?. 11.62 MLD capacity commissioned in 2018. STP is based on ? technique.