214 MW
planned installed capacity of the Yandin Wind Farm located approximately 150km north of Perth and 4km to the south of the Dandaragan township.
-
1,185,754 MWh
proposed to be generated per year.
-
211,742
approximate number of households that can be powered by the farm each year.
-
924,888
estimated reduction in CO2 emissions each year, once the farm is operational.
-
? hectares
Approximate area available for the farm. The wind farm will connect to Western Power’s 330 kV electricity network via a new 10 km transmission line and terminal station that will be built, owned and operated by Western Power.
-
51
Vestas’ 4.2 MW turbines will be used and will deliver a capacity factor of around 50 per cent, putting it at or near the peak of Australian wind farms. Original project approval was for 94 turbines.
-
3
major organisations involved: 1) Project Developer: Alinta Energy, 2) EPC and O&M: Vestas, Decmil 3) PPA: Alinta Energy
-
$400 million
estimated project cost
-
150
peak jobs during construction phase.
-
?
permanent jobs during operational phase.
-
Jul 2019
Estimated start of construction with commissioning in mid 2020.
-
03 Mar 2019
Vestas appointed as EPC partner.
-
Apr 2019
Decmil awarded a $79 million contract for balance of plant works.
-
25 May 2019
Project receives generation license from the Western Australian Economic Regulation Authority.