Dau Tieng Solar Power Complex, Vietnam

Last Modified: Wed Mar 04 2020 21:46:59 GMT+0530 (India Standard Time)
  • 420 MW
    generation capacity of Dau Tieng Solar Power Complex located in Tay Ninh, Vietnam.
  • 688 GWh
    power that will be generated per year. It is estimated that electricity generated by the farm can meet the power demand of Tay Ninh and supply additional power to the southern region.
  • 320,000
    approximate number of households that can be powered by the project each year.
  • ? tonnes
    estimated reduction in CO2 emissions each year, once the project is operational.
  • 540 hectares
    of semi-submerged land at Dau Tieng Lake, the largest manmade lake in the country, has been used for the project.
  • ?
    Number of modules that have been used.
  • ?
    major organisations involved: 1) Project owner and developer: Xuan Cau, B.Grimm. 2) EPC & O&M: ? 3) PPA: ?
  • $391 million
    estimated project cost.
  • ?
    peak jobs during construction phase.
  • ?
    FTE during operational phase.
  • Jun 2018
    Start of construction and took 10 months to complete.
  • 09 Sep 2019
    Official inauguration of the Dau Tieng Solar Power Complex.At the time of the inauguration, the project is the largest of its kind in Southeast Asia. Nguyen Van Binh, head of the Central Economic Commission, said at the inauguration ceremony that the plant would help turn Tay Ninh into one of the country's "capitals" of solar power.